Painting industrial units

We previously painted two units on this site in 2021 and were recently asked to paint the two next door. We have worked for this customer many times.

The units hadn't been painted for a while so there was a lot of cleaning, preparation and repair to carry out before painting could start, about three days in total.

Commercial painting2

Commercial painting3

Once the preparation was complete, it was two days painting to undercoat and gloss the units. Safe access was acheived using a mobile scaffold tower.

Commercial painting6

Commercial painting4

Commercial painting5

We were lucky to have dry sunny weather for the job. We called back the following week to make sure the doors hadn't stuck shut and to take away the "Wet Paint" sign. All was looking good.

The customer has now booked us for some further work.